* Stephenson Locomotive Society data - raw and not yet cross-referenced
|
Works | Stopped | Entry | Departure | Duration | Level of Work | Actual | Mileage |
---|---|---|---|---|---|---|---|
Gorton Works | 27/10/1923 | 16/01/1924 | 82 days | General | |||
Gorton Works | 19/12/1925 | 13/03/1926 | 85 days | General | |||
Gorton Works | 24/09/1927 | 19/11/1927 | 57 days | General | |||
Gorton Works | 27/07/1929 | 21/09/1929 | 57 days | General | Boiler number 66 (Diagram 13) |
||
Gorton Works | 13/06/1931 | 11/07/1931 | 29 days | General | |||
Gorton Works | 11/03/1933 | 08/04/1933 | 29 days | General | Boiler number 1846 (Diagram 13) |
||
Gorton Works | 04/08/1934 | 25/08/1934 | 22 days | General | Boiler number 784 (Diagram 13) |
||
Gorton Works | 18/04/1936 | 09/05/1936 | 22 days | General | Boiler number 1928 (Diagram 13) |
||
Gorton Works | 12/02/1938 | 26/02/1938 | 15 days | General | Boiler number 263 (Diagram 13) |
||
Gorton Works | 23/09/1939 | 14/10/1939 | 22 days | General | Boiler number 3027 (Diagram 13) |
||
Gorton Works | 30/07/1941 | 23/08/1941 | 25 days | General | Boiler number 3029 (Diagram 13) |
||
Gorton Works | 13/10/1943 | 06/11/1943 | 25 days | General | Boiler number 3012 (Diagram 13) |
||
Gorton Works | 27/10/1945 | 24/11/1945 | 29 days | General | Boiler number 583 (Diagram 13) |
||
Gorton Works | 21/12/1946 | 18/01/1947 | 29 days | Light Repair | After collision |
||
Gorton Works | 13/09/1947 | 13/09/1947 | 1 day | Light Repair |
Report Date | Title | Report | Source |
---|---|---|---|
01/11/1948 | Darlington Works | The new Class 'A.1' locomotives, Nos. 60130-33, ex North Road bear Works Nos. 2049-52, in order. A minor change will be noticed in the new Darlington and Doncaster Works plates on the new 'A.1's,' they give the date, Works No. and origin, but no area is given. No. 68051 has been fitted with a modified bunker (and new cab windows), for increased coal capacity. Locomotives awaiting Works:-Nos. 827, 1601/29/30/42/51/55/72, 2992 (to scrap yard), 3007, 3344, 4916, 5710, 7307, 8089, 8400, 8686, 9099, 9392, 69841, 'Austerity' 77329 and Electric 26500. Locomotives ex Works:-Nos. 60507, 60980. 62366, 62711/23/75, 63398, 65028, 65118, 65752/85, 65803/83, 67256/65, 68051, 68395, 68437, 68533, 68675, 69372/92, 69787, 69882/91/93 and- 'Austerity' 77215. Locomotives broken up:-Nos. 1360/78, 5641, 8285, 8400 an 9399. It will be noticed that two of these were ex G.C.R. 'B.7' 4-6-0's. It is pleasing to note that the N.E. Area locomotives. especially Gateshead stock, are approaching their pre-grouping splendour for cleanliness. Some of the 'A.4's' are spotless, while the rest are creditable. |
SLS/194812 |
Date | Event | Details | Source | See Also |
---|---|---|---|---|
05/1922 | To Service | To service as Great Central Railway Number 470 Built at Gorton Works, Works Number Diagram 13 boiler fitted |
||
03/05/1922 | Allocation | Reallocated to Gorton (GOR) | ||
27/10/1923 | Works Visit | Works Visit - Gorton Works (General) - Arr: 27/10/1923. Dep: 16/01/1924. | ||
09/02/1924 | Renumbered | Renumbered to 5470 | ||
21/04/1924 | Allocation | Reallocated to Sheffield Neepsend (SHF) | ||
05/06/1924 | Allocation | Reallocated to Gorton (GOR) | ||
19/12/1925 | Works Visit | Works Visit - Gorton Works (General) - Arr: 19/12/1925. Dep: 13/03/1926. | ||
24/09/1927 | Works Visit | Works Visit - Gorton Works (General) - Arr: 24/09/1927. Dep: 19/11/1927. | ||
27/07/1929 | Works Visit | Works Visit - Gorton Works (General) - Arr: 27/07/1929. Dep: 21/09/1929. Work undertaken: Boiler number 66 (Diagram 13) |
||
13/06/1931 | Works Visit | Works Visit - Gorton Works (General) - Arr: 13/06/1931. Dep: 11/07/1931. | ||
11/03/1933 | Works Visit | Works Visit - Gorton Works (General) - Arr: 11/03/1933. Dep: 08/04/1933. Work undertaken: Boiler number 1846 (Diagram 13) |
||
04/08/1934 | Works Visit | Works Visit - Gorton Works (General) - Arr: 04/08/1934. Dep: 25/08/1934. Work undertaken: Boiler number 784 (Diagram 13) |
||
18/04/1936 | Works Visit | Works Visit - Gorton Works (General) - Arr: 18/04/1936. Dep: 09/05/1936. Work undertaken: Boiler number 1928 (Diagram 13) |
||
04/03/1937 | Allocation | Reallocated to Colwick (CLK) | ||
05/01/1938 | Allocation | Reallocated to Annesley (ANN) | ||
12/02/1938 | Works Visit | Works Visit - Gorton Works (General) - Arr: 12/02/1938. Dep: 26/02/1938. Work undertaken: Boiler number 263 (Diagram 13) |
||
23/09/1939 | Works Visit | Works Visit - Gorton Works (General) - Arr: 23/09/1939. Dep: 14/10/1939. Work undertaken: Boiler number 3027 (Diagram 13) |
||
30/07/1941 | Works Visit | Works Visit - Gorton Works (General) - Arr: 30/07/1941. Dep: 23/08/1941. Work undertaken: Boiler number 3029 (Diagram 13) |
||
13/10/1943 | Works Visit | Works Visit - Gorton Works (General) - Arr: 13/10/1943. Dep: 06/11/1943. Work undertaken: Boiler number 3012 (Diagram 13) |
||
06/11/1943 | Allocation | Reallocated to Gorton (GOR) | ||
27/10/1945 | Works Visit | Works Visit - Gorton Works (General) - Arr: 27/10/1945. Dep: 24/11/1945. Work undertaken: Boiler number 583 (Diagram 13) |
||
15/09/1946 | Allocation | Reallocated to Sheffield Darnall (SHF) | ||
22/11/1946 | Renumbered | Renumbered to 1378 | ||
21/12/1946 | Works Visit | Works Visit - Gorton Works (Light Repair) - Arr: 21/12/1946. Dep: 18/01/1947. Work undertaken: After collision |
||
13/09/1947 | Works Visit | Works Visit - Gorton Works (Light Repair) - Arr: 13/09/1947. Dep: 13/09/1947. | ||
1948 | Number Allocated | Allocated number 61378 but not taken up | ||
19/08/1948 | Withdrawn | Condemned as 1378 from Sheffield Darnall (SHF) | ||
11/1948 | Scrapped | Broken up by Locomotive Works: Darlington |