* Stephenson Locomotive Society data - raw and not yet cross-referenced
|
Works | Stopped | Entry | Departure | Duration | Level of Work | Actual | Mileage |
---|---|---|---|---|---|---|---|
Gateshead Works | 26/09/1923 | 28/11/1923 | 64 days | General | |||
Gateshead Works | 12/05/1925 | 13/08/1925 | 94 days | General | |||
Gateshead Works | 04/07/1927 | 03/10/1927 | 92 days | General | Boiler number D285 (Diagram 63) |
||
Gateshead Works | 12/03/1929 | 17/05/1929 | 67 days | General | |||
Gateshead Works | 03/06/1929 | 18/06/1929 | 16 days | Light Repair | |||
Gateshead Works | 26/02/1931 | 02/04/1931 | 36 days | General | |||
Gateshead Works | 16/04/1931 | 23/04/1931 | 8 days | Painting | Returned to be painted |
||
Darlington Works | 12/12/1932 | 31/01/1933 | 51 days | General | |||
Darlington Works | 23/04/1934 | 05/09/1934 | 136 days | Rebuilding | |||
Darlington Works | 26/08/1935 | 11/10/1935 | 47 days | General | Boiler number D1316 (Diagram 63) |
||
Darlington Works | 23/09/1936 | 20/11/1936 | 59 days | General | Boiler number 2827 (Diagram 63C) |
||
Darlington Works | 08/12/1936 | 09/12/1936 | 2 days | Unclassified | |||
Darlington Works | 20/05/1937 | 22/06/1937 | 34 days | Unclassified | |||
Darlington Works | 11/10/1938 | 26/11/1938 | 47 days | General | |||
Darlington Works | 14/02/1939 | 28/02/1939 | 15 days | Unclassified | |||
Darlington Works | 02/10/1939 | 23/10/1939 | 22 days | Light Repair | |||
Darlington Works | 10/07/1940 | 22/08/1940 | 44 days | Light Repair | |||
Darlington Works | 10/02/1941 | 21/03/1941 | 40 days | General | Boiler number 3066 (Diagram 63B) |
||
Darlington Works | 21/09/1942 | 22/10/1942 | 32 days | General | |||
Darlington Works | 13/01/1943 | 22/01/1943 | 10 days | Unclassified | War damage collision with aircraft at Dinsdale |
||
Darlington Works | 02/06/1944 | 27/06/1944 | 26 days | General | Boiler number 3367 (Diagram 63B) |
||
Darlington Works | 02/08/1944 | 1 day | Weighing | ||||
Darlington Works | 17/11/1945 | 21/12/1945 | 35 days | Light Repair | |||
Darlington Works | 29/06/1946 | 30/08/1946 | 63 days | General | Boiler number 3040 (Diagram 63B) Renumbered to LNER (1946) number 9872 |
||
Darlington Works | 17/12/1946 | 1 day | Weighing | ||||
Gateshead Works | 01/10/1947 | 16/10/1947 | 16 days | Light Repair | |||
Darlington Works | 11/11/1948 | 17/12/1948 | 37 days | General | Boiler number 3908 (Diagram 63B) Renumbered to BR 69872 |
||
Darlington Works | 17/08/1950 | 23/09/1950 | 38 days | General | Positive lub. drive fitted Boiler number 24682 (Diagram 63A) |
||
Darlington Works | 28/09/1950 | 17/10/1950 | 20 days | Unclassified | |||
Darlington Works | 26/05/1952 | 28/06/1952 | 34 days | General | Boiler number 24683 (Diagram 63B) |
||
Darlington Works | 07/07/1952 | 09/07/1952 | 3 days | Unclassified | |||
Darlington Works | 21/04/1954 | 15/05/1954 | 25 days | General | Boiler number 24762 (Diagram 63B) |
||
Darlington Works | 17/05/1954 | 22/05/1954 | 6 days | Unclassified | |||
Darlington Works | 17/02/1955 | 1 day | Weighing | ||||
Darlington Works | 13/01/1956 | 08/02/1956 | 27 days | Light Casual | |||
Darlington Works | 02/05/1956 | 12/06/1956 | 42 days | Heavy Intermediate | |||
Darlington Works | 22/06/1956 | 26/06/1956 | 5 days | Unclassified |
Report Date | Title | Report | Source |
---|---|---|---|
31/10/1957 | Sunderland MPD | This shed now has the following A8's 69852/4/5/8/9/62/72/8/89 and in addition 69873/83/93 are sub-shedded at Durham having replaced G5's. | SLS/195711 |
Date | Event | Details | Source | See Also |
---|---|---|---|---|
06/1920 | To Service | To service as North Eastern Railway Number 1519 Built at Darlington Works, Works Number Allocated to Heaton (HTN) Diagram 63 boiler fitted |
||
26/09/1923 | Works Visit | Works Visit - Gateshead Works (General) - Arr: 26/09/1923. Dep: 28/11/1923. | ||
12/05/1925 | Works Visit | Works Visit - Gateshead Works (General) - Arr: 12/05/1925. Dep: 13/08/1925. | ||
04/07/1927 | Works Visit | Works Visit - Gateshead Works (General) - Arr: 04/07/1927. Dep: 03/10/1927. Work undertaken: Boiler number D285 (Diagram 63) |
||
12/03/1929 | Works Visit | Works Visit - Gateshead Works (General) - Arr: 12/03/1929. Dep: 17/05/1929. | ||
03/06/1929 | Works Visit | Works Visit - Gateshead Works (Light Repair) - Arr: 03/06/1929. Dep: 18/06/1929. | ||
02/04/1930 | Modification | Diagram 63A number 3D/689 boiler fitted | ||
26/02/1931 | Works Visit | Works Visit - Gateshead Works (General) - Arr: 26/02/1931. Dep: 02/04/1931. | ||
16/04/1931 | Works Visit | Works Visit - Gateshead Works (Painting) - Arr: 16/04/1931. Dep: 23/04/1931. Work undertaken: Returned to be painted |
||
12/12/1932 | Works Visit | Works Visit - Darlington Works (General) - Arr: 12/12/1932. Dep: 31/01/1933. | ||
23/04/1934 | Works Visit | Works Visit - Darlington Works (Rebuilding) - Arr: 23/04/1934. Dep: 05/09/1934. | ||
08/09/1934 | Allocation | Reallocated to Darlington (DAR) | ||
26/08/1935 | Works Visit | Works Visit - Darlington Works (General) - Arr: 26/08/1935. Dep: 11/10/1935. Work undertaken: Boiler number D1316 (Diagram 63) |
||
23/09/1936 | Works Visit | Works Visit - Darlington Works (General) - Arr: 23/09/1936. Dep: 20/11/1936. Work undertaken: Boiler number 2827 (Diagram 63C) |
||
08/12/1936 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 08/12/1936. Dep: 09/12/1936. | ||
20/05/1937 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 20/05/1937. Dep: 22/06/1937. | ||
11/10/1938 | Works Visit | Works Visit - Darlington Works (General) - Arr: 11/10/1938. Dep: 26/11/1938. | ||
14/02/1939 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 14/02/1939. Dep: 28/02/1939. | ||
10/04/1939 | Allocation | Reallocated to Saltburn (SALT) | ||
02/10/1939 | Works Visit | Works Visit - Darlington Works (Light Repair) - Arr: 02/10/1939. Dep: 23/10/1939. | ||
10/07/1940 | Works Visit | Works Visit - Darlington Works (Light Repair) - Arr: 10/07/1940. Dep: 22/08/1940. | ||
10/02/1941 | Works Visit | Works Visit - Darlington Works (General) - Arr: 10/02/1941. Dep: 21/03/1941. Work undertaken: Boiler number 3066 (Diagram 63B) |
||
21/09/1942 | Works Visit | Works Visit - Darlington Works (General) - Arr: 21/09/1942. Dep: 22/10/1942. | ||
13/01/1943 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 13/01/1943. Dep: 22/01/1943. Work undertaken: War damage collision with aircraft at Dinsdale |
||
02/06/1944 | Works Visit | Works Visit - Darlington Works (General) - Arr: 02/06/1944. Dep: 27/06/1944. Work undertaken: Boiler number 3367 (Diagram 63B) |
||
02/08/1944 | Works Visit | Works Visit - Darlington Works (Weighing) - Arr: 02/08/1944. | ||
17/11/1945 | Works Visit | Works Visit - Darlington Works (Light Repair) - Arr: 17/11/1945. Dep: 21/12/1945. | ||
29/06/1946 | Works Visit | Works Visit - Darlington Works (General) - Arr: 29/06/1946. Dep: 30/08/1946. Work undertaken: Boiler number 3040 (Diagram 63B) Renumbered to LNER (1946) number 9872 |
||
17/12/1946 | Works Visit | Works Visit - Darlington Works (Weighing) - Arr: 17/12/1946. | ||
01/10/1947 | Works Visit | Works Visit - Gateshead Works (Light Repair) - Arr: 01/10/1947. Dep: 16/10/1947. | ||
11/11/1948 | Works Visit | Works Visit - Darlington Works (General) - Arr: 11/11/1948. Dep: 17/12/1948. Work undertaken: Boiler number 3908 (Diagram 63B) Renumbered to BR 69872 |
||
20/02/1949 | Allocation | Reallocated to West Auckland (AUK) | ||
26/02/1949 | Allocation | Reallocated to West Auckland (AUK) | ||
17/08/1950 | Works Visit | Works Visit - Darlington Works (General) - Arr: 17/08/1950. Dep: 23/09/1950. Work undertaken: Positive lub. drive fitted Boiler number 24682 (Diagram 63A) |
||
28/09/1950 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 28/09/1950. Dep: 17/10/1950. | ||
26/05/1952 | Works Visit | Works Visit - Darlington Works (General) - Arr: 26/05/1952. Dep: 28/06/1952. Work undertaken: Boiler number 24683 (Diagram 63B) |
||
07/07/1952 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 07/07/1952. Dep: 09/07/1952. | ||
21/04/1954 | Works Visit | Works Visit - Darlington Works (General) - Arr: 21/04/1954. Dep: 15/05/1954. Work undertaken: Boiler number 24762 (Diagram 63B) |
||
17/05/1954 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 17/05/1954. Dep: 22/05/1954. | ||
17/02/1955 | Works Visit | Works Visit - Darlington Works (Weighing) - Arr: 17/02/1955. | ||
13/01/1956 | Works Visit | Works Visit - Darlington Works (Light Casual) - Arr: 13/01/1956. Dep: 08/02/1956. | ||
02/05/1956 | Works Visit | Works Visit - Darlington Works (Heavy Intermediate) - Arr: 02/05/1956. Dep: 12/06/1956. | ||
22/06/1956 | Works Visit | Works Visit - Darlington Works (Unclassified) - Arr: 22/06/1956. Dep: 26/06/1956. | ||
15/09/1957 | Allocation | Reallocated to Sunderland (54A) | ||
10/1958 | Scrapped | Scrapped | ||
16/10/1958 | Withdrawn | Condemned as 69872 from Sunderland (52G) |