

|
* Stephenson Locomotive Society data - raw and not yet cross-referenced
|
Works | Stopped | Entry | Departure | Durn | Level of Work | Mileage |
---|---|---|---|---|---|---|
Gorton Works | 01/06/1918 | 16/11/1918 | 169 days | General Boiler number 1484 (Diagram 15) |
||
Gorton Works | 29/01/1921 | 26/02/1921 | 29 days | General | ||
Gorton Works | 28/04/1923 | 28/07/1923 | 92 days | General Boiler number 1949 (Diagram 15) |
||
Gorton Works | 14/02/1925 | 28/03/1925 | 43 days | General Renumbered to LNER (1924) number 5402 |
||
Gorton Works | 21/04/1928 | 26/05/1928 | 36 days | General Boiler number 1510 (Diagram 15) |
||
Gorton Works | 18/01/1930 | 22/02/1930 | 36 days | General | ||
Gorton Works | 08/10/1932 | 15/10/1932 | 8 days | General Boiler number 1854 (Diagram 15) |
||
Gorton Works | 19/10/1935 | 02/11/1935 | 15 days | General Boiler number 1108 (Diagram 15) |
||
Gorton Works | 24/09/1938 | 22/10/1938 | 29 days | General Boiler number 924 (Diagram 15) Fountain lubrication fitted (axleboxes) |
||
Gorton Works | 24/09/1941 | 11/10/1941 | 18 days | General Boiler number 3255 (Diagram 15) |
Date | Event | Details | Source | See Also |
---|---|---|---|---|
02/1912 | To Service | To service as Great Central Railway Number 402 Built at Gorton Works, Works Number Diagram 15 boiler fitted |
||
18/07/1919 | Allocation | Reallocated to Mexborough (MEX) | ||
21/07/1924 | Allocation | Reallocated to Doncaster (DON) | ||
23/08/1924 | Allocation | Reallocated to Mexborough (MEX) | ||
26/10/1941 | Withdrawn | Condemned as 769 from Mexborough (MEX) | ||
26/10/1941 | Renumbered | Renumbered to 769 |

