Works | Stopped | Entry | Departure | Duration | Level of Work | Actual | Mileage |
---|---|---|---|---|---|---|---|
Gorton Works | 16/02/1924 | 26/04/1924 | 71 days | General | Renumbered to LNER (1924) number 6297 |
||
Gorton Works | 18/09/1926 | 20/11/1926 | 64 days | General | |||
Gorton Works | 23/02/1929 | 29/06/1929 | 127 days | General | Boiler number 1224 (Diagram 15) |
||
Gorton Works | 25/07/1931 | 22/08/1931 | 29 days | General | Boiler number 1242 (Diagram 15) |
||
Gorton Works | 19/08/1933 | 02/09/1933 | 15 days | General | Boiler number 1077 (Diagram 15) |
||
Gorton Works | 21/09/1935 | 05/10/1935 | 15 days | General | Boiler number 1443 (Diagram 15) |
||
Gorton Works | 04/09/1937 | 02/10/1937 | 29 days | General | Boiler number 1024 (Diagram 15) |
||
Gorton Works | 16/09/1939 | 23/09/1939 | 8 days | General | Boiler number 3250 (Diagram 15) |
||
Gorton Works | 29/09/1941 | 18/10/1941 | 20 days | General | Boiler number 3423 (Diagram 15) Renumbered to WD 785 |
Date | Event | Details | Source | See Also |
---|---|---|---|---|
06/1919 | To Service | To service as ROD Number 2147 Built at North British Locomotive Company, Glasgow, Works Number 22237 Diagram 15 boiler fitted |
||
09/1919 | Allocation | |||
09/1919 | Renumbered | Renumbered to 2842 | ||
08/1921 | Allocation | |||
16/02/1924 | Works Visit | Works Visit - Gorton Works (General) - Arr: 16/02/1924. Dep: 26/04/1924. Work undertaken: Renumbered to LNER (1924) number 6297 |
||
25/04/1924 | Allocation | Reallocated to Gorton (GOR) | ||
26/04/1924 | To Stock | To LNER stock | ||
03/05/1924 | Allocation | Reallocated to Immingham (IMM) | ||
18/09/1926 | Works Visit | Works Visit - Gorton Works (General) - Arr: 18/09/1926. Dep: 20/11/1926. | ||
15/12/1926 | Allocation | Reallocated to Sheffield Neepsend (SHF) | ||
23/02/1929 | Works Visit | Works Visit - Gorton Works (General) - Arr: 23/02/1929. Dep: 29/06/1929. Work undertaken: Boiler number 1224 (Diagram 15) |
||
05/01/1930 | Allocation | Reallocated to Retford Thrumpton (G.C.) (RET) | ||
25/07/1931 | Works Visit | Works Visit - Gorton Works (General) - Arr: 25/07/1931. Dep: 22/08/1931. Work undertaken: Boiler number 1242 (Diagram 15) |
||
19/08/1933 | Works Visit | Works Visit - Gorton Works (General) - Arr: 19/08/1933. Dep: 02/09/1933. Work undertaken: Boiler number 1077 (Diagram 15) |
||
21/09/1935 | Works Visit | Works Visit - Gorton Works (General) - Arr: 21/09/1935. Dep: 05/10/1935. Work undertaken: Boiler number 1443 (Diagram 15) |
||
04/09/1937 | Works Visit | Works Visit - Gorton Works (General) - Arr: 04/09/1937. Dep: 02/10/1937. Work undertaken: Boiler number 1024 (Diagram 15) |
||
16/09/1939 | Works Visit | Works Visit - Gorton Works (General) - Arr: 16/09/1939. Dep: 23/09/1939. Work undertaken: Boiler number 3250 (Diagram 15) |
||
29/09/1941 | Works Visit | Works Visit - Gorton Works (General) - Arr: 29/09/1941. Dep: 18/10/1941. Work undertaken: Boiler number 3423 (Diagram 15) Renumbered to WD 785 |
||
18/10/1941 | Withdrawn | Condemned as 785 from Retford Thrumpton (G.C.) (RET) |