Works | Stopped | Entry | Departure | Duration | Level of Work | Actual | Mileage |
---|---|---|---|---|---|---|---|
Gorton Works | 26/04/1913 | 05/07/1913 | 71 days | General | |||
Gorton Works | 21/08/1915 | 26/02/1916 | 190 days | General | Boiler number 1414 (Diagram 17Sup) |
||
Gorton Works | 18/09/1920 | 27/11/1920 | 71 days | General | Boiler number 862 (Diagram 17Sat) |
||
Gorton Works | 24/02/1923 | 19/05/1923 | 85 days | General | |||
Gorton Works | 28/11/1925 | 30/01/1926 | 64 days | General | Boiler number 651 (Diagram 17Sup) Renumbered to LNER (1924) number 5963 |
||
Gorton Works | 15/12/1928 | 26/01/1929 | 43 days | General | Modified to conform to LNER Gauge |
||
Gorton Works | 28/02/1931 | 21/03/1931 | 22 days | General | Boiler number 914 (Diagram 17Sat) |
||
Gorton Works | 10/03/1934 | 31/03/1934 | 22 days | General | Boiler number 552 (Diagram 17Sup) |
Date | Event | Details | Source | See Also |
---|---|---|---|---|
1910 | To Service | To service as Great Central Railway Number 963 Built at Gorton Works, Works Number Allocated to Mexborough (MEX) Diagram 17Sup boiler fitted |
||
26/04/1913 | Works Visit | Works Visit - Gorton Works (General) - Arr: 26/04/1913. Dep: 05/07/1913. | ||
21/08/1915 | Works Visit | Works Visit - Gorton Works (General) - Arr: 21/08/1915. Dep: 26/02/1916. Work undertaken: Boiler number 1414 (Diagram 17Sup) |
||
18/09/1920 | Works Visit | Works Visit - Gorton Works (General) - Arr: 18/09/1920. Dep: 27/11/1920. Work undertaken: Boiler number 862 (Diagram 17Sat) |
||
24/02/1923 | Works Visit | Works Visit - Gorton Works (General) - Arr: 24/02/1923. Dep: 19/05/1923. | ||
07/1924 | Allocation | Reallocated to Doncaster (DON) | ||
28/11/1925 | Works Visit | Works Visit - Gorton Works (General) - Arr: 28/11/1925. Dep: 30/01/1926. Work undertaken: Boiler number 651 (Diagram 17Sup) Renumbered to LNER (1924) number 5963 |
||
15/12/1928 | Works Visit | Works Visit - Gorton Works (General) - Arr: 15/12/1928. Dep: 26/01/1929. Work undertaken: Modified to conform to LNER Gauge |
||
24/01/1929 | Allocation | Reallocated to March (MAR) | ||
09/03/1929 | Allocation | Reallocated to Annesley (ANN) | ||
28/02/1931 | Works Visit | Works Visit - Gorton Works (General) - Arr: 28/02/1931. Dep: 21/03/1931. Work undertaken: Boiler number 914 (Diagram 17Sat) |
||
22/05/1931 | Allocation | Reallocated to Ardsley (ARD) | ||
10/03/1934 | Works Visit | Works Visit - Gorton Works (General) - Arr: 10/03/1934. Dep: 31/03/1934. Work undertaken: Boiler number 552 (Diagram 17Sup) |
||
03/10/1936 | Withdrawn | Condemned as 5963 from Ardsley (ARD) |